Renovation planner: your project, week by week
Tell us about your home and the works: the schedule updates as you go. It plans, it does not price: the fixed price comes after the visit.
Your schedule
Duration of the works 2 to 4 weeks
Request a visit with this scheduleRoom-by-room phasing included (occupied home).
- Demolition and removal
- Plumbing
- Electrics
- Waterproofing and screed (drying)
- Tiling
- Plastering and painting
- Fittings and finishing
- Cleaning and handover
- M2 · 20%
- M3 · 30%
- M4 · 30%
- M5 · 15%
Indicative durations in working weeks (5 days), excluding the year-end closure and the building trade holidays, confirmed after the visit.
Detailed schedule (table)
| Trades | W1 | W2 | W3 | W4 |
|---|---|---|---|---|
| Demolition and removal | 3 d | – | – | – |
| Plumbing | 3.5 d | 0.5 d | – | – |
| Electrics | 2 d | – | – | – |
| Waterproofing and screed (drying) | – | 4.5 d | 2.5 d | – |
| Tiling | – | 1 d | 5 d | – |
| Plastering and painting | – | – | 3 d | – |
| Fittings and finishing | – | – | – | 2 d |
| Cleaning and handover | – | – | – | 2 d |
To arrange before the works
- Asbestos survey by a FACH-recognised firm (building older than 1991): 1 to 2 weeks, plus removal if asbestos-containing materials are found.
- Orders to place early: tiles, bathroom furniture, kitchen, parquet. Up to 12 weeks for delivery, so we order as soon as you sign.
Can you stay at home?
Yes
We phase the works to keep a shower room or a kitchen usable, and we clean up every evening.
Milestones and payments
- M2 · Quote and schedule signed20% deposit
- M3 · Demolition and services inspected2nd payment: 30%
- M4 · Finishes installed3rd payment: 30%
- M5 · Handover and acceptance reportBalance: 15% (the 5% retention stays with you)