The starting point

The owners wanted a comfortable, better insulated upper floor without moving out, with a grant application filed before the works.

What we did

  • Staircase closed off with a dust screen, site access from outside.
  • Buildings Programme application filed by the owners before the start, using our description of works.
  • Original cornices and doors removed, restored and refitted.

Trades coordinated

  1. 01 Demolition
  2. 02 Electrics
  3. 03 Plumbing
  4. 04 Internal insulation
  5. 05 Tiling
  6. 06 Plastering and painting
  7. 07 Flooring

Planned schedule, actual schedule

  • Demolition Planned · 5 d Actual · 5 d
  • Electrics and plumbing Planned · 12 d Actual · 12 d
  • Internal insulation Planned · 8 d Actual · 8 d
  • Tiling Planned · 7 d Actual · 7 d
  • Plastering and painting Planned · 15 d Actual · 15 d
  • Flooring and handover Planned · 12 d Actual · 12 d

The gap, explained

A damaged floor joist found under the parquet was reinforced (signed variation, two and a half days).

Similar projects

  • Light kitchen open to the dining area, oak parquet Kitchen · Chêne-Bougeries

    Family house kitchen in Chêne-Bougeries

    A 1969 kitchen renovated in two and a half weeks while the family lived in the house.

    Planned
    2.5 weeks
    Actual
    2.5 weeks
  • Level-access shower in marble-effect porcelain with a glass screen and niche Bathroom · Champel

    Bathroom in a 1965 building in Champel

    A bath replaced by a level-access shower in an occupied apartment. The toilet was back in service every evening.

    Planned
    3.5 weeks
    Actual
    3.8 weeks

Milestone 01

A similar project?