Kitchen · Chêne-Bougeries · 2026
Family house kitchen in Chêne-Bougeries
A 1969 kitchen renovated in two and a half weeks while the family lived in the house.
The starting point
The owners had chosen their kitchen from a kitchen company and needed a contractor to prepare the room and coordinate the fitting.
What we did
- Services positioned from the kitchen designer’s plan and checked together at milestone 3.
- Consumer unit upgraded for the induction hob.
- Temporary kitchen in the utility room for 12 days.
Trades coordinated
- 01 Demolition
- 02 Electrics
- 03 Plumbing
- 04 Plastering and painting
- 05 Flooring
- 06 Kitchen (partner)
Planned schedule, actual schedule
- Demolition
- Electrics and plumbing
- Plastering, painting and flooring
- Kitchen fitting
- Handover
The gap, explained
Schedule kept, no gap.