Bathroom · Rolle · 2024
Grey bathroom in a condominium in Rolle
A 6 m² bathroom in a 1991 building: no compulsory asbestos survey, and three weeks on site as planned.
The starting point
The owner wanted a simpler bathroom and a bigger shower, while keeping a bath for her grandchildren.
What we did
- A larger shower in place of the old cabinet, with the bath kept and re-clad.
- Textured tiles ordered at signature (8-week lead time).
- Neighbours on the landing informed, with the schedule of noisy days.
Trades coordinated
- 01 Demolition
- 02 Plumbing
- 03 Electrics
- 04 Waterproofing
- 05 Tiling
- 06 Finishing
Planned schedule, actual schedule
- Demolition
- Plumbing and electrics
- Waterproofing and tiling
- Finishing and handover
The gap, explained
Schedule kept, no gap.