Common parts · Lancy · 2025
Condominium entrance hall in Lancy
Renovation of the entrance hall of a 24-flat building, done in halves to keep access to the letterboxes and the lift.
The starting point
The condominium’s building manager had to present a priced project to the owners’ meeting, then carry out the works without closing the building entrance.
What we did
- A pack for the owners’ meeting: description, quote, schedule and a proposal to classify the works as “useful” (double majority).
- Works carried out in two halves, with a protected path to the lift.
- Schedule posted in the hall and updated every Friday.
Trades coordinated
- 01 Demolition
- 02 Electrics
- 03 Tiling
- 04 Plastering and painting
- 05 Locksmith (partner)
Planned schedule, actual schedule
- Demolition
- Electrics (lighting)
- Tiling
- Plastering and painting
- Letterboxes and handover
The gap, explained
Schedule kept, no gap.