Kitchen · Nyon · 2025
Kitchen opened onto the living room in Nyon
A non-load-bearing partition removed to open the kitchen onto the living room, with a temporary kitchen set up in the dining room.
The starting point
A family of four wanted an open-plan kitchen without losing the use of a kitchen for three weeks.
What we did
- The partition checked by a partner engineer: not load-bearing, no permit required (art. 68a RLATC, confirmed with the municipality).
- A temporary kitchen with a sink and two-ring hob in the dining room.
- Demolition timed to the delivery date confirmed by the kitchen company.
Trades coordinated
- 01 Demolition
- 02 Light masonry
- 03 Electrics
- 04 Plumbing
- 05 Plastering and painting
- 06 Flooring
- 07 Kitchen (partner)
Planned schedule, actual schedule
- Demolition and opening
- Electrics and plumbing
- Plastering and painting
- Flooring
- Kitchen fitting
- Worktop and handover
The gap, explained
The stone worktop arrived three days later than the supplier’s date: the kitchen was usable with a temporary top in the meantime.